Redfern Tower
Project Details
- Client DEICORP PTY LTD
- Location 1A Lawson Square, Redfern, NSW, 2016
- Duration 12 weeks
Perfect was contracted by Deicorp to undertake commercial demolition works, including the removal and demolition of 4 sets of lifts and across 12 levels. Strip out of entire 12 levels of office building back to concrete shell, each floor being 500m2 each. Including the removal of all existing joinery, floor finishes, ceiling tiles, topping slabs, carpet tiles, floor tiles, redundant services and cladding back to base.
Removal of all the hazardous material within the building fit out as per report, including friable & non-friable asbestos throughout the ceiling space within the services being demolished
Investigation works for the new footings & columns strengthening. Structural demolition, alterations & back propping for the basement level & ground floor which involved the removal of concrete load bearing walls & double brick walls.
Demolition of 12 bathrooms, remove floor tiles, wall tiles, ceiling tiles, fixtures and joinery, various concrete cutting for a material hoist 200mm thick. Cutting and demolition of sup stand walls for material hoist. Removal of render/cladding from 4 columns from all 12 levels. Removal of all redundant equipment, single brick walls in basement. Saw cutting and removal of section of the concrete façade to allow for the installation of a new hoist across 12 levels.
Perfect’s skip bins were used on site for load out all works completed during business hours.